Plateau du Parc block 27 – Construction update August 2021

– In the Block 27 garage, electrical, plumbing, installation of sprinklers and ventilation pipes in progress.

– The frame of block 27 is finished, installation of the interior stairs to come soon. Masonry work has begun and we will start the exterior cladding in September.

– Framing in progress and installation of 2nd floor floors completed. Upcoming installation of 3rd floor floor and walls, 2nd floor balconies and roof installation.